4/20/2026

River Road - road work 4/20 - 6/12

Road work on River Road begins
4/20 and continues through 6/12

 

  • May 1 UPDATE - Edgewater River Road Paving Project
    Crosswalk ADA ramps have been completed up to Hilliard Avenue moving south from the Fort Lee border. Pavers will start manhole and catch basin replacement and re-setting the week of May 4, this work will all be completed between 8am and 5pm Monday through Friday causing lane shifting and slow-moving traffic. Night paving is on schedule to begin the week of Monday, May 18 between 8pm and 6am Monday through Friday.